The Hai Long offshore wind project in Taiwan has finished construction, with all 73 turbines now connected to the grid. Developers Mitsui & Co, Northland Power and Gentari marked the milestone at a ceremony on 17 November 2026. The project adds more than 1 GW of capacity to Taiwan Power Company’s (Taipower) network.
Hai Long offshore wind in numbers
Hai Long combines three wind farms into a single project of more than 1 GW. Its owners call it Asia’s largest single offshore wind project. It was also the first project in the Asia-Pacific region to sign a contract for 14 MW turbines. So 73 turbines of that size add up to about 1,022 MW.
Financing was on a similar scale. In 2023, the project raised TWD117bn ($3.55bn), an offshore wind financing record for the region. Then, in 2026, it secured a further TWD55bn ($1.67bn) through Taiwan’s National Credit Guarantee Mechanism. In total, 35 domestic and foreign lenders took part, backed by export credit agencies from several countries.
A first for corporate power deals
Notably, Hai Long 2A is moving away from Taipower’s feed-in tariff. The project won its site in Taiwan’s Round 2 selection, which sold power to Taipower at a fixed tariff. Now it has signed a corporate power purchase agreement and expects to switch to corporate buyers soon.
The developers say this sets a precedent for Taiwan’s offshore wind market. It links large wind farms with growing corporate demand for green electricity. Therefore, other Round 2 projects may follow the same path.
Local supply chain gains
In addition, Hai Long claims Taiwan’s highest level of local content in offshore wind. Beyond its original pledge of 21 nacelles, it bought another 52 locally assembled nacelles. That supported Siemens Gamesa’s expansion of its Taichung nacelle plant. Also, nine new Taiwanese suppliers joined its approved supplier list.
“The continuity of Taiwan’s energy transition policies has provided the stable foundation needed for international investment,” said Tim Kittelhake, chief executive and project director.
Why the Hai Long offshore wind milestone matters
For Japan’s Mitsui, Canada’s Northland Power and Malaysia’s Gentari, the milestone ends a decade of development and construction. Along the way, the project overcame the pandemic and tough conditions in the Taiwan Strait. Meanwhile, Taiwan gains more than 1 GW of green power. Our story on Ember’s firm power study shows why wind pairs well with solar and batteries.
What to watch next
First, Hai Long must finish the permitting steps for full commercial operation, which it targets in 2027. Second, watch when Hai Long 2A switches to its corporate buyer. Finally, the operations team is building local maintenance capacity, including training for fishers with IOG Wind.
Sources
- Hai Long Offshore Wind: Hai Long, Asia’s Largest Single Offshore Wind Project, Marks Construction Completion
- reNEWS: Hai Long completes offshore construction
- ExchangeRate-API: USD reference rates, 18 November 2026
- Entelera: Ember firm power study: adding wind cuts solar-and-battery costs by nearly a fifth