Energy InsightPower & Grids

Data centre grid costs: US utilities ask FERC to lock in 10-20 year payment deals as PJM seeks faster hook-ups

US transmission utilities have asked FERC to make data centres sign 10 to 20 year contracts covering the grid upgrades they need. At the same time, grid operator PJM has proposed cutting connection studies to 12 months from two years, amid a 6.8 GW supply shortfall.

Data centre grid costs: data centre buildings in Ashburn, Virginia, inside the PJM grid region
Data centre buildings in Ashburn, Loudoun County, Virginia, November 2025. Photo: Theodore Christopher, CC0, via Wikimedia Commons

Data centre grid costs are now at the centre of a big US regulatory fight. This week, utilities that own US transmission lines filed requests with the Federal Energy Regulatory Commission (FERC). They want data centres to sign long contracts for the grid upgrades they need. Depending on the region, those deals would last 10 to 20 years, Latitude Media reported on 18 November 2026.

Meanwhile, grid operators want to connect data centres faster. For example, PJM Interconnection, the biggest US grid, has proposed cutting its connection studies to 12 months from two years.

Why FERC is reviewing data centre grid costs

The filings answer a FERC order from June 2026. In it, the regulator told the six grid operators it oversees to fix the rules for large power users. By 16 November 2026, five had replied. Moreover, the sixth, the Southwest Power Pool, is due to file by 20 November 2026.

Most operator plans focus on speed. For instance, New York and California would let data centres connect sooner. In return, those sites would agree to cut use during grid congestion.

What utilities want data centres to pay

The utilities, by contrast, focus on who pays. In the PJM region, a data centre would pay for at least 80% of the transmission service it requests. That commitment would last at least 10 years. In addition, it would post collateral starting at 25% of what it owes. The guarantee would rise to the full amount when service begins.

Elsewhere, the terms are longer. Utilities in California and New York propose 15 years. Meanwhile, the Midwest grid operator MISO has pitched a three-way contract that could run up to 20 years.

Some utilities already have similar terms at state level. For example, Dominion Energy’s Virginia tariff sets a floor of 85% of contracted transmission demand over 14 years. Similarly, AEP Ohio requires 85% over 12 years.

However, gaps remain. PG&E reports a data centre pipeline of 12.9 GW, yet its retail tariff sets no minimum term. California has passed a law requiring large load tariffs by 2028.

PJM’s plan for faster connections

PJM, which covers 13 states and 67 million people, faces a supply shortfall of about 6.8 GW. Therefore, it wants to study power plants, transmission and large loads such as data centres together. That would also show exactly which upgrades data centres cause, so states can bill them directly.

PJM spokesman Jeff Shields said neither generation nor transmission is coming online quickly enough. Demand growth is coming “mainly” from large loads such as data centres, he added.

Still, the industry’s main trade group has warned the combined process could cause longer delays. PJM has asked FERC to open a 60-day comment period and rule within 120 days.

What to watch next on data centre grid costs

First, comments on several filings are due on 7 December 2026. Second, FERC rejected most of PJM’s last large load plan in October 2026, so it could push back again. Finally, rising demand is also driving storage growth, with US capacity now above 200 GWh.

Written by

Entelera Research

Entelera Research is the editorial team behind Entelera. We cover crude, LNG, power, renewables, policy and geopolitics, looking at energy the way companies have to: supply, demand, margins, policy and risk, with every number linked to its source and a close eye on India and its place in global markets.