India’s battery storage jumps to nearly 10 GWh as curtailment hits 118.6 GW

India's battery storage capacity rose from about 0.7 GWh to nearly 10 GWh in 10 to 11 months, an MNRE official said. Curtailment affected 118.6 GW of renewable capacity in September.

Read the full analysis of this story

Entelera Energy Insight graphic: India's battery storage jumps to nearly 10 GWh as curtailment hits 118.6 GW
Entelera Energy Insight, 25 October 2026. © 2026 Entelera (entelera.com)

India’s battery storage capacity has risen from about 0.7 GWh to nearly 10 GWh in 10 to 11 months. MNRE Joint Secretary JVN Subramanyam gave the figure in an interview. Meanwhile, curtailment affected 118.6 GW of renewable capacity in September.

Why battery storage matters now

Curtailment happens when the grid cannot take all the power that wind and solar plants produce. In particular, transmission lags behind. A line takes about 36 months to build, Subramanyam said. By contrast, a solar or wind project can be ready in 12 to 18 months. Right-of-way disputes and approvals add to the delay.

Therefore, the ministry is pushing on two fronts. First, it wants lines to big hubs such as Khavda finished on time. Second, it is backing storage, including at the distribution level.

What comes next

New lines have recently come online. As a result, the government expects the gap to narrow over the next 18 months. Even so, the 500 GW goal depends on the grid keeping pace.

For more on the grid problem, read our analysis of India’s curtailment and PM-DHARA.

For a deeper analysis, read: Battery Storage in India: ~14x in a Year, but Curtailment Still Hit 118.6 GW

Written by

Entelera Research

Entelera Research is the editorial team behind Entelera. We cover crude, LNG, power, renewables, policy and geopolitics, looking at energy the way companies have to: supply, demand, margins, policy and risk, with every number linked to its source and a close eye on India and its place in global markets.

Follow Entelera on LinkedIn