Prime Minister Narendra Modi has inaugurated new Power Grid Corporation of India schemes in Karnataka. The lines will move more renewable power out of the state. The POWERGRID Karnataka transmission ceremony took place in Bengaluru on 13 November 2026. Two schemes have entered service, and the prime minister laid foundation stones for two more.
Which POWERGRID Karnataka transmission schemes went live
The inaugurated projects include the Phase-II renewable-energy-zone scheme for Koppal-II (phases A and B) and Gadag-II (phase A). They also include the scheme for the 2,500 MW Bidar solar energy zone. Both will take renewable generation from those zones to demand centres across India.
The Bidar scheme, awarded under tariff-based competitive bidding, entered service with effect from 5 October 2026. The Koppal and Gadag scheme followed, with commissioning effective 23 October 2026. POWERGRID has also received the notification of commercial operation. So the POWERGRID Karnataka transmission inauguration marks projects that are already working, not just planned lines.
What comes next at Davanagere and Bellary
Modi also laid foundation stones for two further schemes. One will integrate the Davanagere, Chitradurga and Bellary renewable-energy zones. The other will strengthen the system for additional renewable potential of 0.25 GW at Davanagere and 2.75 GW at Bellary.
That second scheme includes new interconnecting transformers and a second 400 kV double-circuit line between Bellary and Davanagere. POWERGRID has already acquired Bellary Davanagere Power Transmission Limited, the special-purpose company for the work. In March 2025 it also acquired the special-purpose vehicle for the wider Davanagere, Chitradurga and Bellary zone scheme.
Why POWERGRID Karnataka transmission matters
India’s renewable build-out only has value if the grid can move the power. At the same event, the prime minister said the country’s renewable energy capacity has exceeded 300 GW. However, congestion in renewable-energy zones has often left solar and wind plants waiting for evacuation. These Karnataka lines should ease that bottleneck in a state with large solar and wind potential.
The work also sits alongside other South Asian grid and hydro ties. In a separate story today we cover the REC Bhutan hydropower financing MoU. That deal is another attempt to move more clean power towards Indian demand centres.
That combination of live lines and new foundation stones is typical of India’s renewable-energy-zone programme. Generation often arrives before the grid, and then the grid has to catch up. The POWERGRID Karnataka transmission work is an attempt to close that gap in one of the country’s busiest solar and wind states. In addition, the 400 kV Bellary-Davanagere line will be a useful test of how quickly the next tranche can be built.
What to watch
First, watch utilisation on the Bidar, Koppal and Gadag lines. Commissioned capacity only helps if the connected solar and wind plants are also ready. Then look at the construction timetable for the 400 kV Bellary-Davanagere line. Also watch the extra 0.25 GW at Davanagere and 2.75 GW at Bellary. Finally, further renewable-energy-zone schemes will show whether POWERGRID can keep evacuation in step with new generation.
Sources
- Prime Minister’s Office: PM inaugurates development projects in Bengaluru, Karnataka
- PSU Connect: PM Modi Inaugurates POWERGRID RE Transmission Projects in Karnataka
- Power Peak Digest: PM Modi inaugurates two POWERGRID projects, lays foundation for two more
- Entelera: REC Bhutan hydropower MoU explores INR450bn of clean-energy financing