Energy InsightNuclear

Darlington SMR delay: OPG says Canada’s first unit will miss 2030 and its budget

Ontario Power Generation says the first Darlington small modular reactor will miss its October 2030 commercial-operation target and will cost more than the previously disclosed C$7.7bn ($5.5bn). A new cost and schedule assessment is due by mid-2027.

Darlington SMR delay: Darlington Nuclear Generating Station in Ontario, November 2022
Darlington Nuclear Generating Station in Ontario, 13 November 2022. The first SMR is under construction at the same site. Photo: Robert T Bell, CC BY 2.0, via Wikimedia Commons

Ontario Power Generation says the first small modular reactor at Darlington will not start on time. It will also cost more than planned. In its third-quarter results on 10 November 2026, the utility confirmed the Darlington SMR delay. It will push Unit 1 past the October 2030 commercial-operation target. It will also take the bill above the previously disclosed C$7.7bn ($5.5bn).

Why the Darlington SMR delay is happening

The project is known as the Darlington New Nuclear Project. It is the first small modular reactor under construction in the G7 and in Canada. It uses GE Vernova Hitachi’s BWRX-300 design, which has a capacity of 300 MW. OPG says the extra time and cost reflect ongoing first-of-a-kind engineering by the technology supplier. That work, it says, is affecting construction and the supply chain.

The utility has not issued a new date or a new cost. Instead, it is running a full assessment of the budget and schedule. It expects to finish that work by mid-2027. When OPG chose the design in late 2021, it had said the reactor could be ready as early as 2028. So this is a second slip, not the first.

Nicolle Butcher, OPG’s president and chief executive, said the company has made “meaningful progress”. She added that critical work continues every day on site. At the same time, she said it has identified risks that will affect Unit 1’s schedule and budget. She also said OPG will share further information transparently.

Construction is still moving

The Darlington SMR delay is a schedule and cost problem, not a stoppage. OPG has installed a 2.1-million-pound basemat. It calls this the first nuclear foundation laid in Canada in more than 30 years. In the third quarter of 2026 it also completed the first pour for the turbine-building foundation. Moreover, it has assembled the tunnel-boring machine that will dig and line the condenser cooling-water tunnel. Tunnelling is due in the last quarter of 2026.

Those milestones matter because Darlington is the reference plant for later BWRX-300 units. A later start and a higher first-unit cost would feed into other countries’ decisions. That is especially true where governments count on SMRs for data-centre and industrial load.

What the Darlington SMR delay means for new nuclear

Supporters have sold small modular reactors as cheaper and more repeatable than large conventional plants. However, a first-of-a-kind machine still carries first-of-a-kind risk. OPG’s update does not kill the project, but it removes the 2030 certainty that many backers had used in public.

The contrast with faster-to-build gas and storage is already clear in other markets. In today’s Duke Energy carbon plan, North Carolina kept nuclear as an option while adding gas this decade. Buyers will now judge Darlington on the mid-2027 numbers, not on the original timetable.

What to watch

First, watch whether OPG and GE Vernova Hitachi finish the outstanding engineering before that mid-2027 review. Then look for any change in Ontario’s wider nuclear plan, including later Darlington units. Finally, other BWRX-300 customers will study the new cost and date. A slip at the lead plant is hard to ignore.

Written by

Entelera Research

Entelera Research is the editorial team behind Entelera. We cover crude, LNG, power, renewables, policy and geopolitics, looking at energy the way companies have to: supply, demand, margins, policy and risk, with every number linked to its source and a close eye on India and its place in global markets.