Pemex says first oil at the Trion deepwater field could come in December 2027, about six months earlier than planned. Pemex director Juan Carlos Carpio Fragoso set out the new target this week. He also said the state company plans to set aside budget to speed up the work. Australia’s Woodside operates the Pemex Trion project and still lists 2028 as its first-oil goal.
Pemex Trion target versus the approved plan
The development plan approved in 2023 set June 2028 as the start of production. Therefore, a December 2027 start would bring first oil forward by roughly half a year. Carpio Fragoso said Pemex is working with its operating partner on the faster timetable. However, the date still depends on drilling, well completions and the new facilities, Industry & Energy Magazine reported.
Woodside has not changed its own guidance yet. Its project page still targets first oil in 2028. Likewise, its third-quarter update said Trion remained on budget and on schedule for that year.
Pemex Trion progress at the end of Q3 2026
Trion was 71% complete at the end of the third quarter of 2026, Woodside reported. By then, the partners had drilled 10 of the 24 planned wells. They had also installed the first subsea tree on the seabed. Meanwhile, the floating production unit, called Tláloc, had reached 96% completion. In addition, the disconnectable turret now sits in the hull of the floating storage and offloading vessel.
Shipyards in Korea and China are building the two floating units. Workers hired for the project are also training in Korea before they run the facilities.
Why Trion matters for Pemex and Woodside
Trion would be Mexico’s first deepwater oil production. The field lies in the Perdido Fold Belt, in about 2,500 metres of water. It sits roughly 180 km off the coast of Tamaulipas and 30 km south of the US-Mexico maritime border. Pemex found it in 2012. Later, Woodside took over the development through its merger with BHP Petroleum.
Woodside operates Trion with a 60% interest, while Pemex holds 40%. At its peak, the field should produce about 110,000 barrels a day (b/d). For Pemex, that helps its goal of 1.8mn b/d of national output by 2030, along with fields such as Zama. Moreover, an earlier start would bring cash forward for a heavily indebted company. Our story on Pemex Q3 2026 results showed that pressure.
For Woodside, Trion is its first offshore oil development in Mexico. It also sits alongside portfolio moves such as the Woodside Greater Sunrise sale.
Pemex seeks more deepwater partners
Carpio Fragoso also said Pemex wants more partners to explore offshore fields. In particular, the magazine reported that Pemex is looking at offshore options linked to Petrobras, BP and Eni.
What to watch
First, watch whether Woodside updates its first-oil guidance in its next quarterly report. Next, track the sail-away of the Tláloc unit and the well count. Finally, extra Pemex spending on Trion in its 2027 budget would show how serious the December 2027 push is.
For a deeper analysis, read: Mexico Crude Exports: Why an Early Trion Won’t Refill the Maya Gap